Roofing General Application Data (continued)

  1. Where saddles or crickets are formed in back of chimneys, curves or similar vertical surfaces, they shall be carried not less than 10" under the Certi-label™ shakes/shingles.
  2. Step flashing shall be used where vertical surfaces occur in connection with slopes. They shall be formed of separate pieces. Flashing shall extend horizontally not less than 3" and up the vertical wall so that they shall be lapped by the counter flashing not less than 4". It shall be installed in step fashion and each piece shall lap not less than 3" (one flashing installed on each course concealed under the covering course). If other than masonary is used the flashing shall extend up the wall not leas than 3" behind the sheathing paper.
  3. Dormer flashings shall run 3" up ounder the sheathing paper and not less than 3" horizontally.
  4. Window caps and all other projections at points where rain water accumulates must be provided with flashings, such flashings must extenda distance of at least 3" up the wall behind the sheathing paper.
  5. Soil pipes: Metal shall extend no less than 6" in all directions and shall be installed to lap and shed water to the Certi-label™ shakes or shingles below.

    Hips and Ridges
  1. All Certi-label™ shake/shingle hips and ridges shall be of alternate overlap type applied at the same exposure as field of roof and with nails long enough to penetrate into sheathing at least 3/4". Install a strip of felt, eave protection material or metal over hip or ridge under the ridge or hip cap. If longer or shorter ridge cap is used, adjust exposure accordingly.
Valleys
  1. Certi-label™ shakes/shingles extending into the valley shall be sawed to the proper miter.
  2. Do not lay shakes or shingles with grain parallel with the centerline of valleys.
  3. All valleys shall be installed with Certi-label™ shakes/shingles lapping the valley flashing not less than 7"on each side.
  4. On Certi-label™ shingle roofs of less than 6:12 slope, flashing should extend at least 11" on each side.
  5. For Certi-label™ shakes, metal valley sheets shall be center-crimped; of 20" minimum width; underlaid with a strip of Type 30 ASTM Designation 226 (ASTM D226) or ASTM Designation 4869 (ASTM D 4869) roofing felt over the sheathing, and coated with a metal paint.
  6. Valley metals that have proved reliable in a particular geographic region should be selected. Copper flashing: check with local authorities on the durability of copper valleys in your area.
Fasteners - Installation
  1. For projects within 15 miles of salt water - Certi-label roof shakes and shingle shall be secured with two (2) stainless steel type 316 nails.

    For locations outside the 15 mile range of salt water - Certi-label roof shakes and shingles shall be secured with two (2) stainless steel type 304 nails, or hot-dipped zinc coated galvanized nails confirming to minimum standard ASTM A 153 Class D (1.0oz ft2) or better.
    Fasteners shall have a minimum penetration of 3/4" into the sheathing. For sheathing less than 1/2" thickness, the fasteners shall extend throught he sheathing.
  2. Nails shall be driven flush but not so that the nail head crushes the wood. They shall be placed approximately 3/4" to 1" from the side edges of the shakes/shingles and approximately 1 1/2" above the butt line of the following course.
    Each Certi-label™ roof shake/shingle shall be secured with two full-driven, corrosion-resistant fasteners. (Specify size.)
Fasteners - Shingles
  1. Use 3d "box" nails for new roofs with 16" and 18" shingles.
  2. Use 4d "box" nails for new roofs with 24" shingles.
  3. Use 5d "box" nails for over-roofing with 16" and 18" shingles, and for hips and ridges.
Fasteners - Shakes
  1. Use 5d "box" nails for new roofs with 18" straight-split shakes.
  2. Use 6d "box" nails for new roofs with 18" and 24" handsplit-and-resawn shakes.
  3. Use 5d "box" nails for new roofs with 24" tapersplit shakes.
  4. Use 6d "box" nails for new roofs with 18" and 24" taper-sawn.
  5. 6d nails are usually adequate for Certi-label™ shakes, but longer nails shall be used as Certi-label™ shake or shingle thickness or weather exposure dictates.
  6. Always ask the treatment company which fasteners are recommended for use with their pressure-treated Certi-label™ shakes or shingles. Some fasteners are not compatible with treated material.
    Ensure that fasteners used are accepted by your local Building Official.